COVID-19 Update: Construction activities at the project site will continue. The team is taking the necessary precautions to comply with the current orders and for the safety of the workers and community. Click HERE for information on the County’s COVID-19 Update Page.
Schedule Notes:  
  • Starting January 18, 2021, there will be a second shift of painting to avoid interferences when other work is being performed.  The second shift will start at 6pm to 4:30am, Monday-Friday, and be primarily inside enclosures and buildings. This activity is scheduled to be completed by mid-March.

Timeline Overview of Construction - April 2018 to October 2020

(click on audio button in lower left hand corner for sound, for CC version go here)

The Tomahawk Creek Wastewater Facility Expansion began in April 2018 with major construction scheduled to be completed by Spring of 2022.  The long-term infrastructure investment will utilize the latest proven technologies, protect the environment, and improve water quality in Indian Creek and for downstream communities. 

Live on site Webcam - of Tomahawk Creek Wastewater Facility Expansion 
Panorama - of Tomahawk Creek Wastewater Facility Expansion (April 2020) 