SCHEDULE
Construction started April 2018 and will continue through the spring of 2022.
The following activities will be occurring over the next 2 months
Jan - Feb
2021
-
Site paving
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Dec 2020 - Jan 2021
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Nov - Dec
2020
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Oct - Nov
2020
-
Site paving
-
Gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Sept - Oct
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Rd to NB Lee Blvd and will be opening back up in September
-
Site paving
-
Demo of existing Maintenance Bldg and Switchgear, & gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
Aug - Sept
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Rd to NB Lee Blvd
-
Site paving
-
Demo of existing Maintenance Bldg and Switchgear, & gutting of existing Influent Pump Station
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
July - Aug
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Road to NB Lee Boulevard
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Initial equipment startup
Previous activities
June - July
2020
-
Reconstruction of Lee Boulevard – Roadway to be closed from Mission Road to NB Lee Boulevard
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Interior finishes
-
Energization of the facility and initial equipment startup
Previous activities
May - June
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Energization of the facility and initial equipment startup
Previous activities
April - May
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Energization of new Evergy substation
Previous activities
Mar - April
2020
-
Installation of interior process mechanical equipment and piping
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls and piping
-
Installation of electrical equipment
-
Water tightness testing of water-bearing structures
-
Installation of roofing
-
Removal of the tower cranes
Previous activities
Feb - Mar
2020
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls
Previous activities
Jan - Feb
2020
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
-
Installation of interior ductwork, electrical conduit, and plumbing piping
-
Painting of interior walls
Previous activities
Nov - Dec
2019
-
Installation of interior process mechanical equipment and piping.
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Installation of building masonry
-
Installation of precast concrete and structural metals
Previous activities
Sept - Oct
2019
-
Installation of interior process mechanical equipment and piping.
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Installation of building masonry
Previous activities
Aug - Sept
2019
-
Installation of interior process mechanical equipment and piping.
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Installation of building masonry
Previous activities
July - Aug
2019
​​
-
Installation of interior process mechanical equipment and piping
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
Previous activities
Jun-July
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
Previous activities
May - June
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
Previous activities
Apr - May
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Truck hauling of soils offsite
Previous activities
Mar - Apr
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Structural backfill of wastewater treatment buildings
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled piers
-
Truck hauling of soils offsite
-
Tower Crane Mobilization​
-
Tower Crane #3: March 2019
-
Previous activities
Feb - Mar
2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Truck hauling of soils offsite
-
Tower Crane Mobilization:
-
Tower Crane #3: February 2019
-
Previous activities
Dec 2018 - Jan 2019
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Tower Crane Mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
-
Previous activities
Nov - Dec
2018
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process and electrical underground utilities
-
Structural concrete for wastewater treatment basins
-
Drilled Piers
-
Tower crane mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
-
Previous activities
Oct - Nov
2018
-
Installation of new traffic signal at Lee Blvd. & Mission
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Tower Crane Mobilization:
-
Tower Crane #1: November 2018
-
Tower Crane #2: December 2018
-
Tower Crane #3: January 2019
-
Previous activities
Sept - Oct
2018
-
Excavations for new wastewater treatment basins, including rock excavation
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Completion of the Overflow Channel
-
Construction of the Trailer Complex
-
Installation of new traffic signal at Lee Blvd & Mission
Previous activities
Aug - Sept
2018
-
Excavations for new wastewater treatment basins
-
Demolition of existing wastewater treatment structures
-
Process underground utilities
-
Structural concrete for wastewater treatment basins
-
Completion of the Overflow Channel and install of temporary seeding
-
Secondary entrance installation along Lee Blvd
-
Use of soccer fields north of Lee Blvd for construction storage and laydown
Previous Activitiess
July - Aug
2018
-
Excavations for new wastewater treatment basins
-
Demolition of existing wastewater treatment structures
-
New process underground utilities
-
Structural Concrete for wastewater treatment basins
-
Finalizing decommissioning of Facility. Close attention will be paid to demolishing structures in order to minimize odors.
Previous Activities
June - July
2018
-
Utility relocations
-
Earthwork & Excavations
-
Decommissioning of existing plant
-
Demolition
-
Yard Piping
-
Structural Concrete
Previous Activities
May - June
2018
-
Site Fencing
-
Utility relocations
-
Earthwork
-
Demolition
-
Decommissioning of existing plant
-
24/7 Bypass pumping to occur the week of May 14th
Previous Activities
April - May
2018
-
Site Fencing
-
Utility relocations
-
Clear and Grub
-
Earthwork
-
Demolition
-
Decommissioning of existing plant
Groundbreaking Celebration
Thursday
April 12, 2018
For more information go to press release.