COVID-19 Update: Construction activities at the project site will continue. The team is taking the necessary precautions to comply with the current orders and for the safety of the workers and community.
Click HERE for information on the County’s COVID-19 Update Page.
Schedule Notes:  
  • All three tower cranes are anticipated to come down during the week of April 6th.

  • Evergy is planning two continuous activities. They will work through the night starting 3/23 and 3/30. 
    Each activity could take up to 3 days.

  • March and April. Painting crews will be working past 9 pm. 
    Work will be inside buildings and disturbances will be minimal.

  • Some concrete pours will continue during early morning hours in order to avoid traffic and maintain schedule.

Live on site Webcam - of Tomahawk Creek Wastewater Facility Expansion 

The Tomahawk Creek Wastewater Facility Expansion began in April 2018 with major construction scheduled to be completed by Spring of 2022.  The long-term infrastructure investment will utilize the latest proven technologies, protect the environment, and improve water quality in Indian Creek and for downstream communities. 

ABOUT

SCHEDULE

© 2018 Johnson County Wastewater

Tomahawk Creek Wastewater Treatment Facility Expansion Project email & information line: